Phase # 1 Statistics

Total Quantities of Phase # 1
(TP1: Foundations and Ground Engineering)

 

Civil Works

Prestressing operations (76 tendons) 1,140 m
Excavation 400,000 m3
Construction of dewatering well (Library) 20
Construction of dewatering well (Planetarium) 4
Polyethylene for drainage layer 17,656 m2
Sand for drainage layer 3,531.2 m3
Gravel for drainage layer 8,828 m3
Blind concrete (raft foundation) 3,531.2 m3
Horizontal HDPE (raft foundation) 17,656 m2
Vertical HDPE (raft foundation) 6,561 m2
Horizontal Voltex (raft foundation) 17,656 m2
Vertical Voltex (raft foundation) 2,065 m2
Steel installation (raft foundation) 6,035 tons
Reinforced concrete (raft foundation) 21,628.6 m3

 

Jet Grouting

Jet grouting (600) (648 columns) 7,376.9 m
Jet grouting (1200) (2024 columns) 21,847.8 m
Jet grouting (trial test) (26 columns) 265 m
Rock grouting (63 holes) 1,323 m

 

Piles

Piling (working piles) (602 piles) 15,934.6 m
Piling (steel work) 2,769 tons
Piling (trial tests) (5 piles) 131.4 m

 

Diaphragm Wall

Library diaphragm wall (excavation and concreting – 126 panels) 24,732.4 m2
Library diaphragm wall (steel works) 3,199 tons
Planetarium diaphragm wall (excavation and concreting – 28 panels) 3,363 m2
Planetarium diaphragm wall (steel works) 308 tons
Diaphragm wall (3 trial panels) 640 m2